Prameswari, Azzuma (2025) PENERAPAN PRINSIP PARETO DALAM EVALUASI ALTERNATIF PERCEPATAN WAKTU PADA PROYEK PEMBANGUNAN JALAN AKSES DARI ARTERI TAMAN-KRIAN KE PUSPA AGRO TAHAP 1 MENGGUNAKAN CRITICAL PATH METHOD. Undergraduate thesis, UPN Veteran Jawa Timur.
![]() |
Text
21035010020.-cover.pdf Download (1MB) |
![]() |
Text
21035010020.-bab1.pdf Download (340kB) |
![]() |
Text
21035010020.-bab2.pdf Restricted to Repository staff only until 20 June 2027. Download (421kB) |
![]() |
Text
21035010020.-bab3.pdf Restricted to Repository staff only until 20 June 2027. Download (284kB) |
![]() |
Text
21035010020.-bab4.pdf Restricted to Repository staff only until 20 June 2027. Download (2MB) |
![]() |
Text
21035010020.-bab5.pdf Download (143kB) |
![]() |
Text
21035010020.-daftar pustaka.pdf Download (175kB) |
![]() |
Text
21035010020.-lampiran.pdf Restricted to Repository staff only until 20 June 2027. Download (2MB) |
Abstract
The Construction Project of Access Road from Arteri Taman-Krian to Puspa Agro Phase 1 faces constraints on progress delays which where in week 11, the planned progress reached 46.425%, while the actual progress was lower at 35.310%, resulting in a deviation of -11,115%. This delay results in the risk of not achieving the project schedule target and the potential for delay penalties at PHO (Provisional Hand Over). Therefore, it is necessary to evaluate time acceleration alternatives in order to restore the project schedule effectively and efficiently. This research aims to evaluate the causes of delay and design alternatives to accelerate time. The methods used include Pareto principle analysis to identify the main factors causing delays, as well as the Critical Path Method (CPM) to determine the relationship between activities and the normal duration of the remaining work volume. Furthermore, the Time Cost Trade-Off (TCTO) approach is applied to design rescheduling with additional working hours. By using Microsoft Project software, the initial project duration of 88 calendar days was successfully shortened to 69 calendar days after the addition of 3 working hours on 7 dominant works. The Provisional Hand Over (PHO) completion period was set for 73 calendar days. Thus, the acceleration strategy applied succeeded in shortening the project duration by 19 calendar days. The re-analysis showed that there were 10 critical jobs, most of which were dominant jobs from the Pareto principle analysis. The results of this study confirm that an acceleration focus on dominant and critical works can significantly reduce project duration effectively and efficiently.
Item Type: | Thesis (Undergraduate) | ||||||||
---|---|---|---|---|---|---|---|---|---|
Contributors: |
|
||||||||
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) T Technology > TE Highway engineering. Roads and pavements |
||||||||
Divisions: | Faculty of Engineering > Departement of Civil Engineering | ||||||||
Depositing User: | 21-020_Azz Azzuma Prameswari | ||||||||
Date Deposited: | 20 Jun 2025 02:29 | ||||||||
Last Modified: | 09 Jul 2025 05:09 | ||||||||
URI: | https://repository.upnjatim.ac.id/id/eprint/38732 |
Actions (login required)
![]() |
View Item |