Panjaitan, Nita Jesika (2024) ANALISIS KEBUTUHAN TENAGA KERJA MENGGUNAKAN METODE RESOURCE LEVELING PADA PEKERJAAN STRUKTUR UTAMA GEDUNG BERTINGKAT. Other thesis, UPN Veteran Jawa Timur.
Text (Cover)
20035010021._cover.pdf Download (5MB) |
|
Text (Bab 1)
20035010021._bab1.pdf Download (519kB) |
|
Text (Bab 2)
20035010021._bab2.pdf Restricted to Repository staff only until 29 May 2026. Download (1MB) |
|
Text (Bab 3)
20035010021._bab 3.pdf Restricted to Repository staff only until 29 May 2026. Download (715kB) |
|
Text (Bab 4)
20035010021._bab4.pdf Restricted to Repository staff only until 29 May 2026. Download (5MB) |
|
Text (Bab 5)
20035010021._bab 5.pdf Download (460kB) |
|
Text (Daftar Pustaka)
20035010021._daftarpustaka.pdf Download (331kB) |
|
Text (Lampiran)
20035010021._lampiran.pdf Restricted to Repository staff only Download (2MB) |
Abstract
The characteristics of construction projects consist of a series of activities carried out only once and within a specific period. With the increasing development of construction projects today, there are limitations in resource availability, labor imbalances, sharp fluctuations, and the need for significant costs. Labor and costs need to be analyzed based on existing qualifications throughout the project using the resource leveling method and the assistance of Microsoft Project 2013 to achieve efficient and ideal results. Labor analysis is conducted under real field conditions, before the leveling process, and after the leveling process. The allocation of real field labor costs amounted to IDR 201,395,000. Subsequently, the allocation before the leveling process experienced quite sharp fluctuations and exceeded the daily labor availability. After the leveling process, the fluctuations were reduced, and the allocation obtained before the leveling process was 1575 workers, consisting of foremen, carpenters, masons, ironworkers, and laborers, resulting in a total cost of IDR 154,175,000. Whereas after the leveling process, the number of workers obtained was 1540 with the same qualifications as before the leveling process, resulting in a total cost of IDR 150,500,000. Therefore, labor and costs after leveling resulted in the most efficient and ideal allocation. Keywords: Resource Allocation, Resource Leveling, Labor Costs
Item Type: | Thesis (Other) | ||||||||
---|---|---|---|---|---|---|---|---|---|
Contributors: |
|
||||||||
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) | ||||||||
Divisions: | Faculty of Engineering > Departement of Civil Engineering | ||||||||
Depositing User: | Nita Jesika Panjaitan | ||||||||
Date Deposited: | 30 May 2024 01:45 | ||||||||
Last Modified: | 30 May 2024 01:45 | ||||||||
URI: | https://repository.upnjatim.ac.id/id/eprint/23414 |
Actions (login required)
View Item |