Analisis Line Balancing Menggunakan Metode Ranked Positional Weight (RPW) Untuk Meningatkan Produktivitas Proses Produksi Keramik Di PT XYZ

Saputra, Renno Ananda (2026) Analisis Line Balancing Menggunakan Metode Ranked Positional Weight (RPW) Untuk Meningatkan Produktivitas Proses Produksi Keramik Di PT XYZ. Undergraduate thesis, UPN Veteran Jawa Timur.

[img] Text (Cover)
22032010147.-COVER.pdf

Download (637kB)
[img] Text (Bab 1)
22032010147.-Bab1.pdf

Download (325kB)
[img] Text (Bab 2)
22032010147.-Bab2.pdf
Restricted to Repository staff only until 30 August 2029.

Download (469kB)
[img] Text (Bab 3)
22032010147.-Bab3.pdf
Restricted to Repository staff only until 30 August 2029.

Download (378kB)
[img] Text (Bab 4)
22032010147.-Bab4.pdf
Restricted to Repository staff only until 30 August 2029.

Download (620kB)
[img] Text (Bab 5)
22032010147.-Bab5.pdf

Download (293kB)
[img] Text (Daftar Pustaka)
22032010147.-DAFTAR PUSTAKA.pdf

Download (277kB)
[img] Text (Lampiran)
22032010147.-LAMPIRAN.pdf
Restricted to Repository staff only until 30 August 2028.

Download (1MB)

Abstract

PT XYZ is a ceramic manufacturing company. Its production operations currently suffer from an unbalanced distribution of workloads across stations, preventing optimal utilization of production capacity. This situation results in idle time and balance delays, thereby reducing production line efficiency. This study aims to analyze the condition of the production line and propose improvements using the Ranked Positional Weight (RPW) method. Data were collected through direct observation using the stopwatch time study method. The gathered data were used to calculate standard times, construct a precedence diagram, and determine the positional weight of each element as a basis for grouping workstations. The results indicate that the initial configuration of eight stations could be optimized to six workstations without compromising the production process sequence. Following the implementation of the RPW method, the production line achieved an efficiency of 97.49%, a balance delay of 2.51%, and an idle time of 9.35 seconds, alongside an increase in production output by 449 boxes. The findings demonstrate that the method effectively distributes workloads in terms of time, thereby enhancing the efficiency of the ceramic production line at PT XYZ.

Item Type: Thesis (Undergraduate)
Contributors:
ContributionContributorsNIDN/NIDKEmail
Thesis advisorSaifuddin, Joumil AidilNIDN0718036203joumilaidil.ti@upnjatim.ac.id
Thesis advisorWinursito, Yekti CondroNIDN0013089206yekti.condro.ti@upnjatim.ac.id
Subjects: T Technology > TS Manufactures > TS 155-194 Production Management, Operations Management
Depositing User: Renno Ananda Saputra
Date Deposited: 01 Sep 2026 03:23
Last Modified: 01 Sep 2026 03:32
URI: https://repository.upnjatim.ac.id/id/eprint/59341

Actions (login required)

View Item View Item