Saikhu, Dafa Athalla Nabhan (2024) ANALISIS PERBANDINGAN PERCEPATAN WAKTU PADA PENYELESAIAN PROYEK JALAN MENGGUNAKAN METODE CRASH PROGRAM DENGAN ALTERNATIF PENAMBAHAN JAM KERJA DAN TENAGA KERJA. Undergraduate thesis, UPN VETERAN JAWA TIMUR.
Text (Cover)
19035010079.Cover.pdf Download (2MB) |
|
Text (BAB I)
19035010079.BAB I.pdf Download (679kB) |
|
Text (BAB II)
19035010079.BAB II.pdf Restricted to Repository staff only until 31 May 2026. Download (1MB) |
|
Text (BAB III)
19035010079.BAB III.pdf Restricted to Repository staff only until 31 May 2026. Download (930kB) |
|
Text (BAB IV)
19035010079.BAB IV.pdf Restricted to Repository staff only until 31 May 2026. Download (6MB) |
|
Text (BAB V)
19035010079.BAB V.pdf Download (471kB) |
|
Text (Daftar Pustaka)
19035010079.Daftar Pustaka.pdf Download (810kB) |
|
Text (Lampiran)
19035010079.LAMPIRAN.pdf Restricted to Repository staff only Download (10MB) |
Abstract
The road project in Lumajang Regency is one of the projects that experienced delays in work caused by several factors. One of them is uncertain weather such as continuous rain that affected some task cannot be carried out on time or cannot be continued which had an impact on other work. This project has a limited completion time because the road section affects the traffic flow of local mobility and goods distribution on the road that connects Lumajang and Jember Regency. Therefore, the acceleration of working time was executed so that the project got completed on time. The solution that can be used to accelerate project completion time is to carry out a comparative analysis of acceleration of implementation time on projects using the crashing method using alternatives to increase working hours and the number of workers to obtain maximum completion time for work that is on the critical path. In the crashing method, can generate the Crash Duration, Crash Cost, and Cost Slope analysis is carried out on work activities that are crashed. After that, the most efficient results of accelerating the duration of the project were obtained, namely by alternatively adding working hours which could speed up the project completion time by 25 days from the normal completion time of 219 days and a total cost of iv 9.465.138.216,75. Hitting the alternative of adding working hours can exceed the project completion target of the initial project plan duration. Keywords: Time, Cost, Crashing, Addition Working Hours, Addition Human Resources
Item Type: | Thesis (Undergraduate) | ||||||||
---|---|---|---|---|---|---|---|---|---|
Contributors: |
|
||||||||
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) | ||||||||
Divisions: | Faculty of Engineering > Departement of Civil Engineering | ||||||||
Depositing User: | DAFA ATHALLA NABHAN SAIKHU | ||||||||
Date Deposited: | 31 May 2024 07:46 | ||||||||
Last Modified: | 31 May 2024 07:46 | ||||||||
URI: | https://repository.upnjatim.ac.id/id/eprint/23691 |
Actions (login required)
View Item |